Forest Service reopens debate on who guarantees mine cleanup, with a Wyoming project in view

Comments on the national rule are due Dec. 11. At Bear Lodge near Sundance, the proposed mine faces its own review and Wyoming bonding requirements.

A view from Sheep Mountain toward Sundance Mountain and the Bear Lodge Mountains in Crook County, Wyoming. Archive photo by Allen K. Andersen, USGS. · Allen K. Andersen / U.S. Geological Survey
A view from Sheep Mountain toward Sundance Mountain and the Bear Lodge Mountains in Crook County, Wyoming. Archive photo by Allen K. Andersen, USGS. · Allen K. Andersen / U.S. Geological Survey

The Forest Service’s review of a proposed rare-earth mine near Sundance, Wyoming, puts final closure and cleanup at about two years in a proposed 22-year schedule. Who guarantees that work, and when the guarantee must be in place, are questions the public can again weigh in on. In a notice filed for public inspection Wednesday and published Friday, the Forest Service reopened comments on a national proposal for hardrock mining on national forest lands.

The existing federal rule already allows the Forest Service to require a financial guarantee before it approves a mine plan. Under the February proposal, an operator would estimate what it would cost the agency to hire someone else to do the cleanup, including expected inflation and federal contract administration. If the Forest Service accepts a guarantee in phases, the operator would need to cover the highest estimated cost of restoring all disturbed land that remains unreclaimed at any point in that phase. The next phase could begin only after the agency accepts enough assurance for it.

Bear Lodge shows what that distinction can mean on the ground. The Forest Service’s July project notice describes an open pit and haul roads on national forest land in northeastern Wyoming, with processing on private land. It estimates 17 years of mining and identifies water quality and grazing among the issues for a separate environmental review. Rare Element Resources says it plans to reclaim land progressively and would secure a reclamation bond through Wyoming’s Department of Environmental Quality. Restoring land as mining proceeds would affect how much land might need cleanup at any one stage. The bond amount and any mine approval remain matters for separate project review.

The agency says it reopened the national docket after logging communications it received or took part in after the original comment period closed in April. Comments on the proposed federal rules are due Dec. 11 in docket FS-2018-0052. Earlier comments are already on the record. The Bear Lodge project’s own scoping period, which asked about the mine’s environmental effects, closed Aug. 28 under a separate notice.

Archive photo: Allen K. Andersen, U.S. Geological Survey, public domain.